Snapshot: Projects Seeking Priority Distribution in Argentina’s 3Q22 Capacity Auction

Thirty-five Argentine renewable energy projects applied for priority transmission allocation in the latest capacity auction organized by wholesale electricity market administrator Cammesa.

The round – corresponding to 3Q22 – attracted wind and solar photovoltaic projects.

Earlier this year, Cammesa prioritized seven renewable energy projects following a tie-breaking process in the 2Q22 round.

Among the largest in the current cycle is the 202 MW San Luis Norte wind project, owned by Generación Eléctrica Argentina Renovable I, a unit of energy company PCR and steel company ArcelorMittal Acindar. Located in the province of San Luis and built by construction company Semi, the plant is expected to have an initial capacity of 113 MW. Generación Eléctrica Argentina Renovable I is looking for 84 MW of priority distribution. San Luis Norte obtained 36 MW in Cammesa’s 2Q22 call. A 12 MW solar farm on the site is also under consideration.

The largest installed capacity is the Vivaratá wind project of the PCR Luz de Tres Pico unit, under construction in the province of Buenos Aires with a capacity of 399 MW. The initial capacity should be 49.5 MW. Viveratá already has 31.2 MW of priority dispatch.

Amid strained network capacity in some regions, previous rounds ended in a tie-break. Cammesa is analyzing the applications and a final award decision is expected by the end of the month.

Priority transmission allocation is given to projects that seek to participate in the Mater futures market, where generators supply electricity under contracts with large users. Companies concerned about their green credentials are driving demand for electricity from clean sources.

Argentina needs to boost its transmission capacity to support the continued growth of renewables in the windswept south and sunny northwest. Some transmission corridors are heavily congested, which limits the addition of new grid-connected renewable energy plants.

The multilateral IDB recently said it had approved a $1.14 billion decarbonization credit line for Argentina, with part of the resources earmarked for work on the grid.

PROJECTS SEEKING PRIORITY SHIPPING IN CAMMESA’S 3Q22 CALL

Project: Energetics I dilation (wind)
Applicant: Energética Argentina
Project capacity: 49.5 MW
Maximum capacity sought: 29.5 MW
Province: Buenos Aires
Corredo: Comahue

Project: El Alamito (solar)
Applicant: ADI-NQN
Project capacity: 1.2 MW
Maximum capacity sought: 1MW
Province: Neuquen
Corredo: Comahue

Project: Renewable Energies of Hope (solar)
Applicant: Energías Renovables de la Esperanza
Project capacity: 7.5 MW
Maximum capacity sought: 7.5 MW
Province: San Luis
Corridor: Centro

Project: Los Nogales (solar)
Applicant: Energías Renovables Los Nogales
Project capacity: 9.5 MW
Maximum capacity sought: 9.5 MW
Province: San Luis
Corridor: Centro

Project: Los Molles (solar)
Applicant: PV La Perla
Project capacity: 100 MW
Maximum capacity sought: 60MW
Province: Mendoza
Corridor: Cuyo

Project: Helios Santa Rosa II (solar)
Claimant: Tassaroli
Project capacity: 5.2 MW
Maximum capacity sought: 5.2 MW
Province: Mendoza
Corridor: Cuyo

Project: El Carrizal (solar)
Claimant: Surland Cuyana
Project capacity: 39.6 MW
Maximum capacity sought: 16.4 MW
Province: Mendoza
Corridor: Cuyo

Project: Andinos (wind)
Applicant: Parque Eólico Andinos
Project capacity: 131 MW
Maximum capacity sought: 131MW
Province: Neuquen
Corredo: Comahue

Project: Boreas del Norte (wind)
Applicant: Parques Eólicos Boreas del Norte
Project capacity: 100 MW
Maximum capacity sought: 92.4 MW
Province: San Luis
Corridor: Centro

Project: The Elbita II (wind)
Applicant: Geneia
Project capacity: 36 MW
Maximum capacity sought: 36MW
Province: Buenos Aires
Corridor: Costa Atlantica

Project: The Rinconada (wind)
Applicant: Vientos La Riconada
Project capacity: 92.4 MW
Maximum capacity sought: 92.4 MW
Province: Buenos Aires
Corredo: Comahue

Project: Mataco II (wind)
Applicant: Luz de Tres Picos (PCR)
Project capacity: 101 MW
Maximum capacity sought: 36MW
Province: Buenos Aires
Corredo: Comahue

Project: Mataco III (wind)
Applicant: Luz de Tres Picos (PCR)
Project capacity: 101 MW
Maximum capacity sought: 22MW
Province: Buenos Aires
Corredo: Comahue

Project: Vientos Olavarria (wind)
Claimant: Vientos Olavarría
Project capacity: 101 MW
Maximum capacity sought: 54.3 MW
Province: Buenos Aires
Corredo: Comahue

Project: Vivarata (wind)
Applicant: Luz de Tres Picos (PCR)
Project capacity: 399 MW
Maximum capacity sought: 18.3 MW
Province: Buenos Aires
Corridor: Costa Atlantica

Project: Aconcagua (solar)
Claimant: Aconcagua ER
Project capacity: 20 MW
Maximum capacity sought: 20MW
Province: Mendoza
Corridor: Cuyo

Project: Pocito (solar)
Candidate: Thinkable Energy
Project capacity: 5.03 MW
Maximum capacity sought: 5MW
Province: San Juan
Corridor: Cuyo

Project: Las Barranquitas (solar)
Requester: Energy Point
Project capacity: 10 MW
Maximum capacity sought: 10MW
Province: San Luis
Corridor: Centro

Project: Malargue (solar)
Claimant: Aconcagua ER
Project capacity: 25 MW
Maximum capacity sought: 25MW
Province: Mendoza
Corridor: Cuyo

Project: San Rafael Verano I (solar)
Applicant: Verano Capital Solar 2
Project capacity: 100 MW
Maximum capacity sought: 100MW
Province: Mendoza
Corridor: Cuyo

Project: Capiz I (solar)
Applicant: Trancurá Energía
Project capacity: 20 MW
Maximum capacity sought: 20MW
Province: Mendoza
Corridor: Cuyo

Project: Cura Brochero (solar)
Applicant: Parque Solar Cura Brochero
Project capacity: 17 MW
Maximum capacity sought: 17MW
Province: Córdoba
Corridor: Centro

Project: Pampa del Infierno (solar)
Applicant: PS Pampa del Infierno
Project capacity: 100 MW
Maximum capacity sought: 100MW
Province: Chaco
Correspondent: NEA

Project: Villa of María de Río Seco (solar)
Claimant: Villa de María de Río Seco
Project capacity: 20 MW
Maximum capacity sought: 20MW
Province: Córdoba
Corridor: Centro

Project: Santa Clara II (solar)
Candidate: RPG Santa Clara
Project capacity: 100 MW
Maximum capacity sought: 100MW
Province: San Luis
Corridor: Centro

Project: Santa Clara I (solar)
Candidate: RPG Santa Clara
Project capacity: 100 MW
Maximum capacity sought: 100MW
Province: San Luis
Corridor: Centro

Project: Vientos de Dorrego (wind)
Applicant: Vientos de Dorrego
Project capacity: 63 MW
Maximum capacity sought: 63MW
Province: Buenos Aires
Corredo: Comahue

Project: Del Alto Valle (wind)
Applicant: Parque Eólico del Alto Valle
Project capacity: 100 MW
Maximum capacity sought: 100MW
Province: Neuquen
Corredo: Comahue

Project: Wayra I (wind)
Applicant: Autotrol Renovables (Pampa Energía)
Project capacity: 100 MW
Maximum capacity sought: 40MW
Province: Buenos Aires
Corredo: Comahue

Project: Flavors (wind)
Applicant: YPF Energía Electrica
Project capacity: 168 MW
Maximum capacity sought: 100MW
Province: Buenos Aires
Corredo: Comahue

Project: Pampa Energy III (wind)
Applicant: Pampa Energía
Project capacity: 27 MW
Maximum capacity sought: 27MW
Province: Buenos Aires
Corredo: Comahue

Project: General Levalle I (wind)
Claimant: Levalle Eólico I
Project capacity: 64.5 MW
Maximum capacity sought: 17MW
Province: Córdoba
Corridor: Centro

Project: From La Bahía – expansion (wind)
Applicant: Pampa Energía
Project capacity: 50.4 MW
Maximum capacity sought: 14.4 MW
Province: Buenos Aires
Corredo: Comahue

Project: General Levalle II (wind)
Claimant: Levalle Eólico II
Project capacity: 90.3 MW
Maximum capacity sought: 90MW
Province: Córdoba
Corridor: Centro

Project: San Luis Norte (wind)
Applicant: Generación Eléctrica Argentina Renovable I
Project capacity: 202 MW
Maximum capacity sought: 84MW
Province: San Luis
Corridor: Centro

In addition, the Argentine Federal Department of Energy has reportedly given the green light to the signing of a power purchase agreement for a 200 MW expansion project of the Cauchari solar park. Other projects also requesting a PPP with the State are the following:

– The 100 MW Picún Leufú wind project, planned for the province of Neuquén (ADI-NQN)
– The 100 MW Arauco II wind project (stages 5 and 6) and the 50.1 MW Arauco I solar park, proposed for the province of La Rioja (Parque Eólico Arauco)
– The 99.4 MW Arauco II wind project (phases 3 and 4) (Arauco Renovables)